DISMANTLING AND LOADING OF DREDGERS

PROJECT OVERVIEW:

Activity: Dismantling and loading of dredgers
From: Afungi, Mozambique
To: Pemba, Mozambique and Mombasa, Kenya
Place of Execution: Mtwara Port, Tanzania
Period: September till October 2021

SCOPE OF WORK / CLIENT NEEDS

  1. Offloading the Alistair 165ton Crawler crane from the Jumbo barge and keep it on the quayside for the operation.
  2. Dismantle the dredger Ingwenya into three pieces (Ladder, Spud pontoon and spud legs) to reduce weight up to 104ton and loading to the Jumbo barge on route to Pemba Mozambique.
  3. Dismantle the Dredge Pontoon Umkhomo and loading to the Jumbo barge on route to Pemba Mozambique
  4. Dismantle T-Piece and Ten Piece Pontoon and loading to Sky 2 barge on route to Mombasa Kenya

CHALLENGES THAT WE’VE EXPERIENCED:

During the operation of complex lifting activities, there are many challenges that need to be tackled. For this specific project, we faced the absence of a spreader bar to execute the tandem lift of 104 tons, as well as the absence of lifting slings and shackles of 50tons.

In addition, during the loading of T-Piece Pontoon into SKY 2 Barge, we notice that the weight of Pontoon was exceeded due to the amount of water. The operation was stopped for hours to let water drain.

SERVICES SOLUTION:

The operation succeeded due to the reasons lifted below:

  1. The procure of new shackles 50ton was done from the head office
  2. Port cooperation on the other requirements needed for the operation
  3. Engagement of our well-trained riggers and banksman

 

   

   